The following table gives capital costs and variable costs for a coal plant, a natural gas combined‐cycle plant, and a natural‐gas‐fired gas turbine:


COAL
CC
GT
Capital Cost ($/kW)

$ 1,500.00
$ 1,000.00
$ 500.00
Variable Cost (c/kWh)
2.50
4.00
8.00


The utility uses a fixed charge rate of 0.10/yr for capital costs. Its load duration curve is shown as follows:


a.       Draw the screening curves for each type of power plant.

b.       Suggest a least‐cost combination of power plants for this utility.

c.        Estimate the capacity factor for each type of power plant.

d.       How much electricity would each type of power plant generate each year?

e.       What annual revenue would the utility need to receive from each type of power plant?

f.         What would be the cost of electricity from each type of power plant?